Machine Body Material | Mild Steel |
Total Installed Capacity | 4000 Kgs (24 Hrs) |
Technology | Indigenous |
Required Processing Area | 3000 Sft |
Required Manpower | 10 |
Required Total Electricity Load | 35 kW |
Required Total Water | 8000 Ltr Per Day |
Power & Fuel | Electricity / Diesel |
Required List Of Major Raw Materials | Sugar , Food Chemicals, Flavors |
Required List Of Packing Materials | Laminate, Cbb,Tape |
Time To Start The Unit | 90 Days Till Indian Port , + 15 Days To Destination +15 Days For Erection = 120 Days |